City Avenue Project
In the summer of 2021, in response to aging and failing sanitary sewer and stormwater systems near City Ave, BSB initiated design for an upgrade

Ewart Avenue Stormwater Project
In February 2025, Beckley experienced heavy rainfall that caused high water around town and destroyed the stormwater system on Ewart Avenue near the Exhibition Coal

Osprey Road Stormwater Project
In the fall of 2024, BSB’s contractor replaced 80 feet of large stormwater line under Osprey Rd. The metal pipes under the road had badly

Evans Street Project
The Evans Street project was initiated to address deteriorating stormwater pipes in a residential area. Our team’s survey and design work identified the need for
Controlling Stormwater in the Cloud